Our projects

Tech-BF-052

Carrying out works on tightening the bolts of the metal structures of the supporting frame, technological platforms, and stair flights at various levels of the main […]

Tech-BF-050

Inspection and maintenance of ventilation systems on the territory of "Shymkentcement" JSC

Tech-BF-048

Installation of a thermal ventilation system at the packaging area of finished products of OF-1 BGOK

Tech-BF-046

Installation of an oil accounting and control system on all heavy mining and auxiliary equipment, compatible with the ORACLE program

Tech-BF-044

Washing, cleaning, and disinfecting the water supply and distribution system of Aktogay GOK facilities (twice a year)

Tech-BF-042

Maintenance of HVAC equipment in buildings and structures of the mine for the years 2023–2025

Tech-BF-040

Repair/reconstruction works of Kazakhtelecom power transmission lines

Tech-BF-038

Cleaning of the mixed motor oil tank at the Ground Force oil distribution station at the central warehouse

Tech-BF-036

Installation of an automated control system for heating, ventilation, and air conditioning (HVAC) at substation 3320-ER-307

Tech-BF-034

Repair of the Petro Kazakhstan gearbox using Metalock technology

Tech-BF-032

Replacement of filter media at the water treatment station in shift camp No. 2

Tech-BF-030

Provision of labor resources for the maintenance and repair of geomembrane covering at the enrichment plants for processing sulfide and kaolinized ores

Tech-BF-028

Maintenance of control and safety systems at the "Beineu-Bozoi-Shymkent" Gas Pipeline: Periodic maintenance of control and safety systems.

Tech-BF-026

Installation of low-voltage systems on the access railway for monitoring the safety of operations for the delivery and removal of wagons

Tech-BF-024

Replacement of thermal insulation of external pipelines of the water treatment station and installation of a well on the "raw" water pipeline in the territory of […]

Tech-BF-022

Replacement of filter media at the Sewage Treatment Plant

Tech-BF-020

Provision of labor resources for inspections, lubrication, and repair of equipment at the Concentration Plants

Tech-BF-018

Works on the repair/reconstruction of communication lines/linear-cable structures; Repair of 6–10 kV cable lines;

Tech-BF-016

Commissioning of the 4th injection compressor Karachaganak Petroleum Operating B.V.: Commissioning of 4ICP.

Tech-BF-014

Provision of services for the replacement of filter media at the water treatment station of the shift camp

Tech-BF-012

Maintenance of heat exchangers for the cooling system of the gearless drive of the semi-autogenous grinding (SAG) mill and ball mills.

Tech-BF-010

Flushing, cleaning, and disinfection of the reservoir, water supply, and water distribution system of the Bozshakol GOK facilities (annually)

Tech-BF-008

Modification of the water treatment installation at TCO: Transfer of RC500 controllers to Honeywell C300.

Tech-BF-006

Repair and restoration work on the large boiler house of the shift camp, electric boilers, piping, and shut-off valves

Tech-BF-004

Cleaning of the suction and discharge pipelines of peristaltic pumps for copper concentrate No. 463, 464, 465 with a length of 575 meters at the sulfide […]

Tech-BF-002

Replacement of filter media at the water treatment station of shift camp No. 1 BGOK

Tech-BF-051

Installation of anchorage points for safety systems on the equipment of the Concentration Plants of KAZ Minerals Bozshakol LLP

Tech-BF-049

Construction and installation works for the arrangement of additional ventilation and aspiration systems. Installation of a scrubber system

Tech-BF-047

Installation of supply and exhaust ventilation in the ALS laboratory on the territory of the ZIF in Akbakay

Tech-BF-045

Disinfection and cleaning of drinking water reservoirs and pipelines by LLP "Tepke"

Tech-BF-043

Inspection, adjustment, survey, maintenance, and repair of wells on the fire pipeline, fire hydrants, fire valves, internal and external fire gates, and internal and external fire […]

Tech-BF-041

Commissioning of the Vesda fire system at NCOC: Commissioning of the aspirating fire alarm system.

Tech-BF-039

Conducting maintenance and repair of scrubber systems in the production laboratory

Tech-BF-037

Sealing (preservation) of the water intake well No. 1 of the tailings dam at the Bozshakol deposit

Tech-BF-035

Turnkey works for the development of the project and installation of an alkali dosing unit for the neutralizer and control of the pH value of wastewater

Tech-BF-033

Replacement of filter media in the shift camp at the deposit in 2022

Tech-BF-031

Replacement, pressure testing, and cleaning of the pipeline system and tank of the Ground Force oil distribution station in the maintenance and repair shop for quarry […]

Tech-BF-029

Maintenance of APS (automatic crossing signaling) in the amount of 5 units

Tech-BF-027

Commissioning of FGP control systems at TCO: Cyclical inspections and functional tests.

Tech-BF-025

Maintenance and repair of scrubber and ventilation systems of the central analytical laboratory

Tech-BF-023

Services for the installation of a thermal ventilation system at the pumping station for the disposal of enrichment sands at the kaolin ore beneficiation plant

Tech-BF-021

Repair and maintenance of elevators in the new shift camp of the GOK in 2021-2023

Tech-BF-019

Modernization of the nitrogen station at the tire fitting section for heavy mining equipment at MMA

Tech-BF-017

Maintenance of telescopic dispersion systems (TDS)

Tech-BF-015

Development of a SCADA system for well control at TCO: Automation of the wellhead.

Tech-BF-013

Provision of services for flushing 1500 m of pipelines at the flotation and thickening unit

Tech-BF-011

Conducting maintenance for 20,000 operating hours on direct-drive compressors Hertz HSC 55D

Tech-BF-009

Repair and restoration work on the small boiler house of the shift camp, electric boilers, piping, and shut-off valves

Tech-BF-007

Modernization and modification of the liquefied gas system at TCO: Transfer of old Allen-Bradley controllers to Honeywell C300 and Safety Manager.

Tech-BF-005

Cleaning of the suction and discharge pipelines of screw pumps No. 402, 406, with a length of 175 meters at the sulfide plant

Tech-BF-003

Development of a substation automation system at TCO: Automation of electrical substations.

Tech-BF-001

Comprehensive works on the operation and maintenance of external engineering infrastructure facilities - domestic sewage networks on the territory of the sulfide plant (OF-1)

Const-CC-43

Replacement of window blocks

Const-CC-42

Manufacture and installation of the shelter for the oil station 3330-LU-110

Const-CC-41

Construction and installation works: “Modification of the aspiration system at the packaging and shipment area of concentrate”

Const-CC-40

Installation of bus stops at the RAV/LAB, MMA, Oir, OF-2, and packaging area sections

Const-CC-39

Conducting construction and installation works for the concreting of the foundation for the pump 35ZP-RU-468A at the copper concentrate thickening area of the Aktogay-2 Sulfide Plant

Const-CC-38

Conducting construction and installation works for the technical water pipeline with the installation of water cannons at the animal care area of plots 160/161/162

Const-CC-37

Repair of floors with polyurethane-cement coating in the maintenance building of BGOK, 2100 sq.m

Const-CC-36

Reinforcement of the southern eroded slope in the area of the Alarko warehouse at the Bozshakol deposit

Const-CC-35

Inspection, adjustment, examination, maintenance, and repair of wells on the fire pipeline, fire hydrants, fire valves, internal and external fire gates, internal and external fire water […]

Const-CC-34

Service contract for the maintenance and repair of buildings and structures of FOK

Const-CC-33

Repair/reconstruction works of Kazakhtelecom power transmission lines

Const-CC-32

Laying of the pedestrian walkway from the Central Control and Dispatch Point (CCDP) to the bus stop of the shift camp

Const-CC-31

Repair of the 2nd floor office, dining room, safety coordinator's office, metallurgists' office, and meeting room of OF-2 at the kaolin ore processing plant

Const-CC-30

Repair of floors with polyurethane-cement coating in the maintenance building of BGOK, 1300 sq.m

Const-CC-29

Installation of anchor points for fall protection systems on the equipment of the enrichment plants of KAZ Minerals Bozshakol

Const-CC-28

Concreting the foundation for pump 3445-PU-406A in the collective flotation area

Const-CC-27

Installation of an automated control system for heating, ventilation, and air conditioning (HVAC) at substation 3320-ER-307

Const-CC-26

Manufacture and installation of protective barriers for OF-1 BLOCK

Const-CC-25

Turnkey works for the development of the project and installation of the alkali dosing unit and pH control system for wastewater

Const-CC-24

Conducting fireproofing treatment of the wooden structure in the sports complex

Const-CC-23

Repair and reconstruction works of fences, doors, gates, and turnstile systems at gas distribution stations.

Const-CC-22

Major repair of the hangar at the mining and processing plant (GOK).

Const-CC-21

Concreting the foundation for pump 3340-PU-333 (350G-MSU-G), and installation of pump 3340-PU-333 (3500-MCU-G) in the modification building of the Sulfide Plant

Const-CC-20

Provision of insulation services for the covering in the attic spaces of the shift camp

Const-CC-19

Application of horizontal and vertical color markings, safety signs, and informational signs at the central warehouse

Const-CC-18

Repair of the electrical service premises of OG-2 and the general service control point-220kV with the installation of walls and ceilings made of non-combustible materials

Const-CC-17

Repair of the central analytical laboratory building in 2022

Const-CC-16

Manufacture and installation of fences for the conveyor park of OF-1 BGOK

Const-CC-15

Replacement of thermal insulation of external pipelines at the water treatment station and installation of a well on the "raw" water pipeline in the territory of […]

Const-CC-14

Services for the installation of a thermal ventilation system at the pumping station for the disposal of enrichment sands at the kaolin ore processing plant of […]

Const-CC-13

Installation of anchor points for the safe execution of ongoing construction, repair, and preventive maintenance work on the roof structures of the scrubber building and the […]

Const-CC-12

Replacement of window blocks in the lantern structure of the electrolysis workshop at the Oxide Plant site.

Const-CC-11

Cosmetic repair of the Station building at Bozshakol station.

Const-CC-10

Installation of metal bumpers along the ground conveyor CV-102 at the mining and processing plant (GOK).

Const-CC-09

Repair/reconstruction works of communication lines/linear-cable structures; Repair of 6-10 kV cable lines;

Const-CC-08

Painting and varnishing of containers at the central warehouse of BGOK.

Const-CC-07

Construction and installation works for the arrangement of additional exhaust ventilation and aspiration systems. Installation of a scrubber system.

Const-CC-06

Repair works in the central analytical laboratory building

Const-CC-05

Repair and restoration works on the roof of the core storage building with the installation of a pavement around the building

Const-CC-04

Reconstruction of the existing hangar into a grain storage facility

Const-CC-03

Installation of a thermal ventilation system at the packaging area of the finished products of sulfide production

Const-CC-02

Replacement of windows in the RAV building of BGOK

Const-CC-01

Construction and installation works of inspection wells. Cleaning of pipelines of the circulating water supply systems of the tailing facilities of enrichment plant No. 1.

Des-CS-14

Author supervision for the project "Water supply, heating, and fire extinguishing system of shift camp No. 2"

Des-CS-13

Development of the major repair project for the 7 km section of the Aktogay station - Kola village highway

Des-CS-12

Development of a modernization project for the aspiration system at the concentrate packaging and shipment station KBL

Des-CS-11

Research and consulting services for improving the use of fluoroplastic filters in membrane bioreactors, with subsequent reporting and data transfer for Karabatan Utility Solution

Des-CS-10

Design of the construction project: "Water supply, heating, and fire extinguishing systems of the shift camp"

Des-CS-09

Development of passports and determination of the efficiency of ventilation installations at the mining and processing plant (MPC)

Des-CS-08

Development of a working project for connecting the building in the quarry to internal communications

Des-CS-07

Author supervision for the project "Design of 6/0.4 kV substations and modernization of the electrical network of the production laboratory"

Des-CS-06

Engaging a design organization to prepare defect lists during reconstruction, major, and current repairs of buildings, structures, and engineering systems

Des-CS-05

Author supervision for the project "Development of a modernization project for the aspiration system at the concentrate packaging and shipment station"

Des-CS-04

Development of working documentation for the major repair of substations (bk/vd 0.4 kV): boiler houses No. 1 and No. 2, transformer substations No. 1, 2, 3, […]

Des-CS-03

Development of the modernization project for the aspiration system at the packaging and shipment station of KAL concentrate.

Des-CS-02

Design of 6/04 kV substations and modernization of the electrical network of the production laboratory.

Des-CS-01

Development of project documentation "Installation of additional exhaust ventilation and aspiration systems in the production laboratory of KAZ Minerals Bozshakol"

Asp-BFE-22

Design, equipment supply, and construction and installation works: "Modification of the aspiration system at the concentrate packaging and shipment site"

Asp-BFE-21

Author supervision for the project "Development of a modernization project for the aspiration system at the concentrate packaging and shipment station"

Asp-BFE-20

Audit of aspiration systems

Asp-BFE-19

Construction and installation works for the arrangement of additional exhaust ventilation and aspiration systems. Installation of a scrubber system

Asp-BFE-18

Development of a project for the aspiration system at the concentrate packaging and shipment station

Asp-BFE-17

Aspiration of the seed plant

Asp-BFE-16

Technical maintenance and scheduled preventive repair of industrial aspiration complexes at factories processing judge and kaolinized ores for 2019–2024.

Asp-BFE-15

Development of project documentation "Arrangement of additional exhaust ventilation and aspiration systems in the production laboratory of LLP "KAZ Minerals Bozshakol"

Asp-BFE-14

Aspiration of the dry mix mixer

Asp-BFE-13

Aspiration of the grain elevator at the bread factory

Asp-BFE-12

Aspiration of the elevator

Asp-BFE-11

Aspiration of the spring production line

Asp-BFE-10

Aspiration of the packaging machine

Asp-BFE-09

Aspiration of the air chute

Asp-BFE-08

Aspiration of the pellet production line. Explosion protection of the aspiration system

Asp-BFE-07

Telescopic sleeves for loading non-granulated meal into open vehicles

Asp-BFE-06

Aspiration of the paint production line

Asp-BFE-05

Aspiration of the belt conveyors of the port elevator. Explosion protection of the aspiration system

Asp-BFE-04

Aspiration of the cake mix production line. Explosion protection of the aspiration system.

Asp-BFE-03

Aspiration of the kiln in gypsum production

Asp-BFE-02

Centralized dust collection system of the foundry shop

Asp-BFE-01

Spark capture system for the aspiration system

Tech-BF-052

23
Carrying out works on tightening the bolts of the metal structures of the supporting frame, technological platforms, and stair flights at various levels of the main […]

Tech-BF-050

22
Inspection and maintenance of ventilation systems on the territory of "Shymkentcement" JSC

Tech-BF-048

service13
Installation of a thermal ventilation system at the packaging area of finished products of OF-1 BGOK

Tech-BF-046

21
Installation of an oil accounting and control system on all heavy mining and auxiliary equipment, compatible with the ORACLE program

Tech-BF-044

20
Washing, cleaning, and disinfecting the water supply and distribution system of Aktogay GOK facilities (twice a year)

Tech-BF-042

19
Maintenance of HVAC equipment in buildings and structures of the mine for the years 2023–2025

Tech-BF-040

18
Repair/reconstruction works of Kazakhtelecom power transmission lines

Tech-BF-038

17
Cleaning of the mixed motor oil tank at the Ground Force oil distribution station at the central warehouse

Tech-BF-036

16
Installation of an automated control system for heating, ventilation, and air conditioning (HVAC) at substation 3320-ER-307

Tech-BF-034

15
Repair of the Petro Kazakhstan gearbox using Metalock technology

Tech-BF-032

2
Replacement of filter media at the water treatment station in shift camp No. 2

Tech-BF-030

14
Provision of labor resources for the maintenance and repair of geomembrane covering at the enrichment plants for processing sulfide and kaolinized ores

Tech-BF-028

13
Maintenance of control and safety systems at the "Beineu-Bozoi-Shymkent" Gas Pipeline: Periodic maintenance of control and safety systems.

Tech-BF-026

n200918s[1]
Installation of low-voltage systems on the access railway for monitoring the safety of operations for the delivery and removal of wagons

Tech-BF-024

144220
Replacement of thermal insulation of external pipelines of the water treatment station and installation of a well on the "raw" water pipeline in the territory of […]

Tech-BF-022

15
Replacement of filter media at the Sewage Treatment Plant

Tech-BF-020

14427
Provision of labor resources for inspections, lubrication, and repair of equipment at the Concentration Plants

Tech-BF-018

1442131
Works on the repair/reconstruction of communication lines/linear-cable structures; Repair of 6–10 kV cable lines;

Tech-BF-016

12
Commissioning of the 4th injection compressor Karachaganak Petroleum Operating B.V.: Commissioning of 4ICP.

Tech-BF-014

service14
Provision of services for the replacement of filter media at the water treatment station of the shift camp

Tech-BF-012

myw1
Maintenance of heat exchangers for the cooling system of the gearless drive of the semi-autogenous grinding (SAG) mill and ball mills.

Tech-BF-010

z53qyekg[1]
Flushing, cleaning, and disinfection of the reservoir, water supply, and water distribution system of the Bozshakol GOK facilities (annually)

Tech-BF-008

11
Modification of the water treatment installation at TCO: Transfer of RC500 controllers to Honeywell C300.

Tech-BF-006

7
Repair and restoration work on the large boiler house of the shift camp, electric boilers, piping, and shut-off valves

Tech-BF-004

3
Cleaning of the suction and discharge pipelines of peristaltic pumps for copper concentrate No. 463, 464, 465 with a length of 575 meters at the sulfide […]

Tech-BF-002

2
Replacement of filter media at the water treatment station of shift camp No. 1 BGOK

Tech-BF-051

10
Installation of anchorage points for safety systems on the equipment of the Concentration Plants of KAZ Minerals Bozshakol LLP

Tech-BF-049

service15
Construction and installation works for the arrangement of additional ventilation and aspiration systems. Installation of a scrubber system

Tech-BF-047

ventil_4_med[1]
Installation of supply and exhaust ventilation in the ALS laboratory on the territory of the ZIF in Akbakay

Tech-BF-045

scale_1200-3-768x512[1]
Disinfection and cleaning of drinking water reservoirs and pipelines by LLP "Tepke"

Tech-BF-043

9
Inspection, adjustment, survey, maintenance, and repair of wells on the fire pipeline, fire hydrants, fire valves, internal and external fire gates, and internal and external fire […]

Tech-BF-041

8
Commissioning of the Vesda fire system at NCOC: Commissioning of the aspirating fire alarm system.

Tech-BF-039

7
Conducting maintenance and repair of scrubber systems in the production laboratory

Tech-BF-037

6
Sealing (preservation) of the water intake well No. 1 of the tailings dam at the Bozshakol deposit

Tech-BF-035

5
Turnkey works for the development of the project and installation of an alkali dosing unit for the neutralizer and control of the pH value of wastewater

Tech-BF-033

csm_AW2_f1e79a2b49[1]
Replacement of filter media in the shift camp at the deposit in 2022

Tech-BF-031

144023
Replacement, pressure testing, and cleaning of the pipeline system and tank of the Ground Force oil distribution station in the maintenance and repair shop for quarry […]

Tech-BF-029

4
Maintenance of APS (automatic crossing signaling) in the amount of 5 units

Tech-BF-027

3
Commissioning of FGP control systems at TCO: Cyclical inspections and functional tests.

Tech-BF-025

2
Maintenance and repair of scrubber and ventilation systems of the central analytical laboratory

Tech-BF-023

image;s=1000x700[1]
Services for the installation of a thermal ventilation system at the pumping station for the disposal of enrichment sands at the kaolin ore beneficiation plant

Tech-BF-021

22
Repair and maintenance of elevators in the new shift camp of the GOK in 2021-2023

Tech-BF-019

gen_azot_kislorid_375x180[1]
Modernization of the nitrogen station at the tire fitting section for heavy mining equipment at MMA

Tech-BF-017

144242
Maintenance of telescopic dispersion systems (TDS)

Tech-BF-015

Rigquip-rigpartner[1]
Development of a SCADA system for well control at TCO: Automation of the wellhead.

Tech-BF-013

service12
Provision of services for flushing 1500 m of pipelines at the flotation and thickening unit

Tech-BF-011

666-3
Conducting maintenance for 20,000 operating hours on direct-drive compressors Hertz HSC 55D

Tech-BF-009

666-1
Repair and restoration work on the small boiler house of the shift camp, electric boilers, piping, and shut-off valves

Tech-BF-007

386476864_323448430371149_3873340215469696191_n
Modernization and modification of the liquefied gas system at TCO: Transfer of old Allen-Bradley controllers to Honeywell C300 and Safety Manager.

Tech-BF-005

6
Cleaning of the suction and discharge pipelines of screw pumps No. 402, 406, with a length of 175 meters at the sulfide plant

Tech-BF-003

projects1
Development of a substation automation system at TCO: Automation of electrical substations.

Tech-BF-001

1
Comprehensive works on the operation and maintenance of external engineering infrastructure facilities - domestic sewage networks on the territory of the sulfide plant (OF-1)

Const-CC-43

144216
Replacement of window blocks

Const-CC-42

36
Manufacture and installation of the shelter for the oil station 3330-LU-110

Const-CC-41

35
Construction and installation works: “Modification of the aspiration system at the packaging and shipment area of concentrate”

Const-CC-40

normand_143511661[1]
Installation of bus stops at the RAV/LAB, MMA, Oir, OF-2, and packaging area sections

Const-CC-39

34
Conducting construction and installation works for the concreting of the foundation for the pump 35ZP-RU-468A at the copper concentrate thickening area of the Aktogay-2 Sulfide Plant

Const-CC-38

33
Conducting construction and installation works for the technical water pipeline with the installation of water cannons at the animal care area of plots 160/161/162

Const-CC-37

promyshlennyi-nalivnoi-pol-200x150[1]
Repair of floors with polyurethane-cement coating in the maintenance building of BGOK, 2100 sq.m

Const-CC-36

32
Reinforcement of the southern eroded slope in the area of the Alarko warehouse at the Bozshakol deposit

Const-CC-35

9
Inspection, adjustment, examination, maintenance, and repair of wells on the fire pipeline, fire hydrants, fire valves, internal and external fire gates, internal and external fire water […]

Const-CC-34

main-1-1[1]
Service contract for the maintenance and repair of buildings and structures of FOK

Const-CC-33

18
Repair/reconstruction works of Kazakhtelecom power transmission lines

Const-CC-32

31
Laying of the pedestrian walkway from the Central Control and Dispatch Point (CCDP) to the bus stop of the shift camp

Const-CC-31

30
Repair of the 2nd floor office, dining room, safety coordinator's office, metallurgists' office, and meeting room of OF-2 at the kaolin ore processing plant

Const-CC-30

29
Repair of floors with polyurethane-cement coating in the maintenance building of BGOK, 1300 sq.m

Const-CC-29

10
Installation of anchor points for fall protection systems on the equipment of the enrichment plants of KAZ Minerals Bozshakol

Const-CC-28

1521735951-9[1]
Concreting the foundation for pump 3445-PU-406A in the collective flotation area

Const-CC-27

16
Installation of an automated control system for heating, ventilation, and air conditioning (HVAC) at substation 3320-ER-307

Const-CC-26

27
Manufacture and installation of protective barriers for OF-1 BLOCK

Const-CC-25

5
Turnkey works for the development of the project and installation of the alkali dosing unit and pH control system for wastewater

Const-CC-24

28
Conducting fireproofing treatment of the wooden structure in the sports complex

Const-CC-23

tipovye-resheniya-dlya-promzona[1]
Repair and reconstruction works of fences, doors, gates, and turnstile systems at gas distribution stations.

Const-CC-22

sklad-angar_2[1]
Major repair of the hangar at the mining and processing plant (GOK).

Const-CC-21

1521735951-9[1]
Concreting the foundation for pump 3340-PU-333 (350G-MSU-G), and installation of pump 3340-PU-333 (3500-MCU-G) in the modification building of the Sulfide Plant

Const-CC-20

1398814554_2-mansarda-iznutri[1]
Provision of insulation services for the covering in the attic spaces of the shift camp

Const-CC-19

7ca9f719ba727469b6a8665d855cacab[1]
Application of horizontal and vertical color markings, safety signs, and informational signs at the central warehouse

Const-CC-18

arenda_ofisnyh_zdaniy_containex[1]
Repair of the electrical service premises of OG-2 and the general service control point-220kV with the installation of walls and ceilings made of non-combustible materials

Const-CC-17

service16
Repair of the central analytical laboratory building in 2022

Const-CC-16

27
Manufacture and installation of fences for the conveyor park of OF-1 BGOK

Const-CC-15

144220
Replacement of thermal insulation of external pipelines at the water treatment station and installation of a well on the "raw" water pipeline in the territory of […]

Const-CC-14

Prin_003[1]
Services for the installation of a thermal ventilation system at the pumping station for the disposal of enrichment sands at the kaolin ore processing plant of […]

Const-CC-13

26
Installation of anchor points for the safe execution of ongoing construction, repair, and preventive maintenance work on the roof structures of the scrubber building and the […]

Const-CC-12

144216
Replacement of window blocks in the lantern structure of the electrolysis workshop at the Oxide Plant site.

Const-CC-11

25
Cosmetic repair of the Station building at Bozshakol station.

Const-CC-10

07[1]
Installation of metal bumpers along the ground conveyor CV-102 at the mining and processing plant (GOK).

Const-CC-09

1442131
Repair/reconstruction works of communication lines/linear-cable structures; Repair of 6-10 kV cable lines;

Const-CC-08

proizvodstvo_kontejnerov_razlichnyx_vidov[1]
Painting and varnishing of containers at the central warehouse of BGOK.

Const-CC-07

24
Construction and installation works for the arrangement of additional exhaust ventilation and aspiration systems. Installation of a scrubber system.

Const-CC-06

service16
Repair works in the central analytical laboratory building

Const-CC-05

my2
Repair and restoration works on the roof of the core storage building with the installation of a pavement around the building

Const-CC-04

my3
Reconstruction of the existing hangar into a grain storage facility

Const-CC-03

service13
Installation of a thermal ventilation system at the packaging area of the finished products of sulfide production

Const-CC-02

okna_na_proizvodstvennom[1]
Replacement of windows in the RAV building of BGOK

Const-CC-01

5
Construction and installation works of inspection wells. Cleaning of pipelines of the circulating water supply systems of the tailing facilities of enrichment plant No. 1.

Des-CS-14

23
Author supervision for the project "Water supply, heating, and fire extinguishing system of shift camp No. 2"

Des-CS-13

23
Development of the major repair project for the 7 km section of the Aktogay station - Kola village highway

Des-CS-12

23
Development of a modernization project for the aspiration system at the concentrate packaging and shipment station KBL

Des-CS-11

23
Research and consulting services for improving the use of fluoroplastic filters in membrane bioreactors, with subsequent reporting and data transfer for Karabatan Utility Solution

Des-CS-10

23
Design of the construction project: "Water supply, heating, and fire extinguishing systems of the shift camp"

Des-CS-09

14423
Development of passports and determination of the efficiency of ventilation installations at the mining and processing plant (MPC)

Des-CS-08

666
Development of a working project for connecting the building in the quarry to internal communications

Des-CS-07

666
Author supervision for the project "Design of 6/0.4 kV substations and modernization of the electrical network of the production laboratory"

Des-CS-06

23
Engaging a design organization to prepare defect lists during reconstruction, major, and current repairs of buildings, structures, and engineering systems

Des-CS-05

666
Author supervision for the project "Development of a modernization project for the aspiration system at the concentrate packaging and shipment station"

Des-CS-04

666
Development of working documentation for the major repair of substations (bk/vd 0.4 kV): boiler houses No. 1 and No. 2, transformer substations No. 1, 2, 3, […]

Des-CS-03

666
Development of the modernization project for the aspiration system at the packaging and shipment station of KAL concentrate.

Des-CS-02

666
Design of 6/04 kV substations and modernization of the electrical network of the production laboratory.

Des-CS-01

666
Development of project documentation "Installation of additional exhaust ventilation and aspiration systems in the production laboratory of KAZ Minerals Bozshakol"

Asp-BFE-22

35
Design, equipment supply, and construction and installation works: "Modification of the aspiration system at the concentrate packaging and shipment site"

Asp-BFE-21

2019-12-08_00-52-20[1]
Author supervision for the project "Development of a modernization project for the aspiration system at the concentrate packaging and shipment station"

Asp-BFE-20

tex_audit[1]
Audit of aspiration systems

Asp-BFE-19

service15
Construction and installation works for the arrangement of additional exhaust ventilation and aspiration systems. Installation of a scrubber system

Asp-BFE-18

2019-12-08_00-52-20[1]
Development of a project for the aspiration system at the concentrate packaging and shipment station

Asp-BFE-17

6[1]
Aspiration of the seed plant

Asp-BFE-16

4
Technical maintenance and scheduled preventive repair of industrial aspiration complexes at factories processing judge and kaolinized ores for 2019–2024.

Asp-BFE-15

2019-12-08_00-52-20[1]
Development of project documentation "Arrangement of additional exhaust ventilation and aspiration systems in the production laboratory of LLP "KAZ Minerals Bozshakol"

Asp-BFE-14

42
Aspiration of the dry mix mixer

Asp-BFE-13

20200130_113920[1]
Aspiration of the grain elevator at the bread factory

Asp-BFE-12

41
Aspiration of the elevator

Asp-BFE-11

40
Aspiration of the spring production line

Asp-BFE-10

img_20160328_163048-1000x1000[1]
Aspiration of the packaging machine

Asp-BFE-09

39
Aspiration of the air chute

Asp-BFE-08

pellet-1[1]
Aspiration of the pellet production line. Explosion protection of the aspiration system

Asp-BFE-07

38
Telescopic sleeves for loading non-granulated meal into open vehicles

Asp-BFE-06

3-cartridge-dust-collectors[1]
Aspiration of the paint production line

Asp-BFE-05

37
Aspiration of the belt conveyors of the port elevator. Explosion protection of the aspiration system

Asp-BFE-04

rsbp_b-flap_i_vmp[1]
Aspiration of the cake mix production line. Explosion protection of the aspiration system.

Asp-BFE-03

MG_1426-scaled[1]
Aspiration of the kiln in gypsum production

Asp-BFE-02

cat_pig-iron_600_400[1]
Centralized dust collection system of the foundry shop

Asp-BFE-01

Spark-Trap-01[1]
Spark capture system for the aspiration system